Has anyone compelled the County Surveyor to file a map per 8768.5 because they took too long to provide comments? If so, was the board involved?
Any information is appreciated.
8768.5 ministerial filing
-
wingding
- Posts: 78
- Joined: Sun May 10, 2015 9:04 am
Re: 8768.5 ministerial filing
How long?
My 2 mains counties are currently taking 12-14 months or 6-7 months.
My 2 mains counties are currently taking 12-14 months or 6-7 months.
-
Brad L
- Posts: 43
- Joined: Thu Jul 23, 2015 11:33 am
Re: 8768.5 ministerial filing
I'm at 4 months without any comments from the CS so far. I've had a few push up to 6 months, but that is including comments and resubmittals, which is acceptable.
It's crazy that the TPM, demo plans, & final map for my project are getting reviewed faster than a RoS.
I appreciate the reply.
It's crazy that the TPM, demo plans, & final map for my project are getting reviewed faster than a RoS.
I appreciate the reply.
Brad Luken