Hello all
I have a question for the forum. If I have a client who needs to do a Lot Line Adjustment and owns 8 contiguous parcels. Can I do two LLAs of four lots each at the same time? Or do I have to wait until the first one is done, then submit the second?
There are no parcels in common between the two LLAs, they simply share one common boundary line. So they are contiguous.
The land use attorney says we have to wait until the first one is completed to start the second.
Anyone have experience with this?
Thanks, Lynn
Lot Line Adjustments with Adjoining Boundaries
- polaris
- Posts: 35
- Joined: Mon Jul 27, 2015 2:27 pm
-
mpallamary
- Posts: 3466
- Joined: Tue Mar 11, 2008 2:12 pm
Re: Lot Line Adjustments with Adjoining Boundaries
Yes, you can.
You do not have the required permissions to view the files attached to this post.
- polaris
- Posts: 35
- Joined: Mon Jul 27, 2015 2:27 pm
Re: Lot Line Adjustments with Adjoining Boundaries
Mike
That is the decision about sequential LLAs. Not about contiguous LLAs. I've seen the case and the amicus curae.
But I am asking about doing two side by side LLAs for the same owner. No overlap, no waiting period.
That is the decision about sequential LLAs. Not about contiguous LLAs. I've seen the case and the amicus curae.
But I am asking about doing two side by side LLAs for the same owner. No overlap, no waiting period.
-
mpallamary
- Posts: 3466
- Joined: Tue Mar 11, 2008 2:12 pm
Re: Lot Line Adjustments with Adjoining Boundaries
I worked on a project in Cathedral City where, as I recall, they adjusted 150 or more lots at the same time.
I have attached a few of the documents. The entire file is too large to attach. The City relied on the decision I sent over.
I have attached a few of the documents. The entire file is too large to attach. The City relied on the decision I sent over.
You do not have the required permissions to view the files attached to this post.
- Ian Wilson
- Posts: 1087
- Joined: Sat Aug 03, 2002 6:58 am
- Location: Bay Area
Re: Lot Line Adjustments with Adjoining Boundaries
As long as there is no overlap in the parcels, these are two separate LLAs, NOT contiguous or sequential.
Ian Wilson, P.L.S. (CA / NV / CO)
Alameda County Surveyor
Alameda County Surveyor