Expiration of Tentative Map
Posted: Mon Jan 25, 2010 10:40 am
SMA section 66463.5 (b) states
"... Once a timely filing is made, subsequent actions of the local agency, including, but not limited to, processing, approving, and recording, may lawfully occur after the date of expiration of the tentative map. Delivery to the county surveyor or city engineer [surveyor] shall be deemed a timely filing for purposes of this section."
Our City has a situation where a final map was submitted for approval last year, and the Certificate of Acceptance of tax bonds pursuant to SMA section 66492 and 66493 has not been issued. The planners are desirous of returning the signed mylars to the developer's surveyor in order to stop the tolling of the tentative map approval.
My initial reaction, as City Surveyor, is to continue to keep possession of the mylars. The technical aspects of the final map are complete. Planning's concern is that the developer may withold executing the tax bonds indefinitely. The final map will, of course, not be submitted for City Council approval without the tax bonds being in place.
Is this a scenario anyone else has encountered during this slow economy?
Warren
"... Once a timely filing is made, subsequent actions of the local agency, including, but not limited to, processing, approving, and recording, may lawfully occur after the date of expiration of the tentative map. Delivery to the county surveyor or city engineer [surveyor] shall be deemed a timely filing for purposes of this section."
Our City has a situation where a final map was submitted for approval last year, and the Certificate of Acceptance of tax bonds pursuant to SMA section 66492 and 66493 has not been issued. The planners are desirous of returning the signed mylars to the developer's surveyor in order to stop the tolling of the tentative map approval.
My initial reaction, as City Surveyor, is to continue to keep possession of the mylars. The technical aspects of the final map are complete. Planning's concern is that the developer may withold executing the tax bonds indefinitely. The final map will, of course, not be submitted for City Council approval without the tax bonds being in place.
Is this a scenario anyone else has encountered during this slow economy?
Warren