Section 8726 (a) “Land surveying defined†of the LS Act has always confused me. It reads:
“Locates, relocated, establishes, reestablishes, or retraces the alignment or elevation for any of the fixed works embraced within the practice of civil engineering, as described in Section 6731.â€
Section 8728 “Restriction on design†reads:
“Surveys authorized under this chapter do not include the design, either in whole or in part, of any structure or fixed works embraced within the practice of civil engineering.â€
Does 8726 (a) allow the Land Surveyor to establish the elevation of a storm drain or is that considered designing? Section 8726 does not allow the LS to size storm drain, but does it allow the LS to establish the alignment and elevations or is this what Section 8728 is trying to restrict? What is the "legal" answer and does that differ from the "standard practice" answer?
It is fairly obvious that when construction staking off of a grading plan, that any problems with the plan and its relationship to the field conditions needs to be brought up to the engineer of work. Whoever is responsible for the plans is responsible for the design (this is not my question).
Thanks,
Ben
“Locates, relocated, establishes, reestablishes, or retraces the alignment or elevation for any of the fixed works embraced within the practice of civil engineering, as described in Section 6731.â€
Section 8728 “Restriction on design†reads:
“Surveys authorized under this chapter do not include the design, either in whole or in part, of any structure or fixed works embraced within the practice of civil engineering.â€
Does 8726 (a) allow the Land Surveyor to establish the elevation of a storm drain or is that considered designing? Section 8726 does not allow the LS to size storm drain, but does it allow the LS to establish the alignment and elevations or is this what Section 8728 is trying to restrict? What is the "legal" answer and does that differ from the "standard practice" answer?
It is fairly obvious that when construction staking off of a grading plan, that any problems with the plan and its relationship to the field conditions needs to be brought up to the engineer of work. Whoever is responsible for the plans is responsible for the design (this is not my question).
Thanks,